November 19, 2026
A household that closes on a Hampton home this winter is buying a commute across a bridge-tunnel built for 70,000 vehicles a day that now carries close to 100,000. If the schedule holds, the household will own that home when the crossing doubles to eight lanes, sometime in 2027. The September sales numbers don't show the coming change in Hampton prices yet. Hampton's median sales price rose 1.7% from September 2025 to September 2026, close to Norfolk's 1.85% and far behind Virginia Beach's 8.4%.
So a Hampton buyer this season pays a price set by today's four-lane crossing for a home that will likely sit beside an eight-lane one. If you are relocating, especially to a Southside duty station, and comparing Phoebus, Fox Hill, Buckroe or Downtown Hampton against a Norfolk address, it should be part of how you weigh the two.
The HRBT Expansion runs about 10 miles of I-64 across the mouth of the James River, from Mallory Street in Hampton to Patrol Road in Norfolk. Right now two tubes each carry two lanes. When the project is finished there will be eight lanes across the harbor, plus wider shoulders that give stalled cars and emergency vehicles room. VDOT project director Ryan Banas told WHRO in April that the extra lanes and the shoulder improvements will probably do the most for traffic.
Here is the timeline a buyer should keep in mind, from the most recent public documents:
All of these are scheduled dates, and the schedule has slipped once already. Even so, for a buyer signing a contract this winter, the eight-lane crossing is due well inside a normal ownership period, and for many military households inside a single tour.
Before the tunnels open, Hampton may see the express lanes. On Nov. 11, VDOT announced that parts of the Newport News segment (4A/4B) and the Hampton segment (4C) of the Hampton Roads Express Lanes Network could open as early as December 2026. The remaining eastbound Hampton section will follow in a later phase. According to WAVY's report on the announcement, the existing HOV lane in each direction becomes an express lane for 10.5 miles, from just west of Jefferson Avenue to I-664. In the last mile, between I-664 and LaSalle Avenue, one general-purpose lane in each direction becomes an express lane.
Hampton drivers can already see the work. The same update said the new eastbound Hampton River bridge is complete. Final paving and permanent markings are done on I-64 from North Armistead Avenue to Settlers Landing Road, and crews have repaved parts of Rip Rap Road, King Street, River Street and Settlers Landing Road. December is a target, not a confirmed opening date. Contract completion for the Newport News segment is scheduled for spring 2027.
Hampton's 1.7% year-over-year gain matched Portsmouth's and landed between Newport News at 1.63% and Norfolk at 1.85%. Virginia Business reported the same city-level gains on Oct. 19.
The regional supply numbers point the same way. REIN, the region's multiple listing service, counted 6,357 active listings in September 2026. That is up 16.17% from a year earlier and the most homes for sale in Hampton Roads since April 2020. Months of supply rose to 2.97 from 2.63 a year earlier, and median days on market went to 30 from 27. Pending sales for the month fell 6.95% year over year, and the regional median sales price was $375,000, up 2.74%. REIN's 2026 board president said the six-year high in inventory gives buyers extra bargaining room at a time when mortgage rates are trending up.
Taken together, a Hampton buyer this winter has more homes to choose from, more time per listing and more room to negotiate than at any point in the last six years. The price reflects the crossing as it is today. Local real estate leaders have talked about the expansion as something that may change how people think about living on the Peninsula. Hampton Roads Realtors Association President Jay Mitchell told The Virginian-Pilot in August 2025 that "it may offer an opportunity for people to be less concerned about travel." He was describing a possibility. Hampton's September price gain does not show that shift yet.
The Hampton end of the project is in Phoebus, where I-64 meets Mallory Street. In July 2024, VDOT moved both directions of Mallory Street traffic onto the first finished half of the replacement bridge so the old half could be torn down and rebuilt. The new bridge includes pedestrian and bicycle lanes, retaining walls and new signals. The project's scope also includes new sound-barrier walls along the corridor. If you are looking at a home close to the interstate in Phoebus, check which side of a planned wall it would face.
Closures still turn up in VDOT's weekly reports. The Oct. 23 report scheduled an overnight closure of the I-64 east on-ramp at Mallory Street (Exit 268) for Oct. 26–27, and it listed a long-term lane reduction from three lanes to two between Settlers Landing Road/Woodland Road (Exit 267) and LaSalle Avenue (Exit 265A) as part of the Hampton express-lanes work. The HRBT Expansion traffic alerts page has the current list. If you plan to commute, test-drive it on a weekday morning and again on a weekday evening before you write an offer.
Phoebus itself keeps adding businesses. WTKR reported in May 2025 that Grey Goose had moved to Phoebus from elsewhere in Hampton and that its owner was opening an attached fresh-food space. At Fort Monroe, a developer announced a $20 million plan in February 2026 to turn the former hospital and the adjacent arsenal into about 85 apartments, with a target of early 2028, according to WTKR. For more on everyday life in these areas, our Hampton fall calendar covers the Phoebus and Fort Monroe weekends.
Plenty of Peninsula households compare Hampton and Norfolk because of a job at or near Naval Station Norfolk. For them, the expansion is one part of a longer corridor. When it is finished there will be four lanes in each direction across the harbor, two general-purpose and two express, and the express lanes will carry buses too, according to WHRO. As of VDOT's July 2026 network page, express lanes were already running in Norfolk and Chesapeake, with construction underway in Hampton, Norfolk and Newport News. Once the Peninsula segments and the new tunnels open, a commute from Hampton to the Southside will have its own lane choice for the full trip, something no Hampton address has today. VDOT's 64 Express Lanes page shows which segments are open as they come online, and when you test-drive the route before an offer, check that page so you drive the version of it you would actually use.
The project is a regional investment. More than 90% of the cost, about $3.7 billion of the $3.9 billion total, is paid locally through regional sales and gas taxes, Hampton Roads Transportation Accountability Commission Executive Director Todd Halacy told WHRO.
When will the new HRBT tunnels open? VDOT's contract dates call for substantial completion on Feb. 26, 2027, and final completion on Aug. 27, 2027. In August 2026 the project team said it was on track for substantial completion sometime in 2027.
When could the Hampton express lanes open? VDOT said on Nov. 11 that parts of the Newport News and Hampton segments could open as early as December 2026, with the remaining eastbound Hampton section to follow in a later phase.
Are Hampton prices rising faster because of the project? Not as of September 2026. Hampton's 1.7% annual median gain was in line with Norfolk, Portsmouth and Newport News.
If you're weighing a Hampton address against Norfolk and want an offer that reflects this winter's inventory and the 2027 crossing schedule, Kristie Weaver can drive the route with you and build a negotiation plan around what Hampton sellers face this season. Relocating on orders? Start with our military relocation page and we'll take it from there.